constraints
A scheduling protocol that establishes when a Task should happen. Constraints (which can be flexible or inflexible) are: ASAP - As soon as possible (no real constraint). ALAP - As late as possible. FNET - Finish no earlier than. SNET - Start no earlier than. FNLT - Finish no later than. SNLT - Start no later than. MFO - Must finish on. MSO - Must start on. See also: Deadline. SOURCE; microsoft project glossary-projectlearning.net
|