estimate to complete ("etc")

The expected additional cost of an activity, a group of activities, or of the project when the defined scope of work is completed. Most techniques for forecasting ETC include some adjustment of the original cost estimate based on project performance to date. See also earned value and estimate at completion.

SOURCE: apm.org

The value expressed in either dollars or hours developed to represent the cost of the work required to complete a task. Cobra calculates the ETC by subtracting the budgeted cost of work performed from the budget at complete. The ETC is calculated as BAC - BCWP.